Project map 

We worked with our contractor to align our project schedule with other work underway in the area, to minimise the impact on customers and to minimise extra disruptions.

The below map shows the staged approach.
Stage 1 = Orange, Stage 2 = Purple, Stage 3 = Blue, Stage 4 = Yellow.

Project map 
The below map shows the staged approach.
Stage 1 = Yellow,  Stage 2 = Orange, Stage 3 = Green, Stage 4 = Black.

Any questions?

Large infrastructure projects like this one can take time to deliver. We will aim to complete this project within the scheduled timeframe, but please be aware these dates are subject to change, and we will keep you updated as the project progresses, if this is the case.

We thank the local community for their understanding as we carry out this improvement work and apologise in advance for any inconvenience and disruption that may be caused. 

Get in touch